4 min read | Updated on November 17, 2026, 13:18 IST
SUMMARY
The Maharashtra Forest Department had ordered an immediate halt to construction on November 13 over the absence of prior National Board for Wildlife (NBWL) approval.
Stock list

Adani Green Energy shares fell 4% to an intraday low of ₹1,247.95 after its earnings announcement. | Image: Shutterstock
Adani Green Energy Ltd (AGEL) on Monday said its 1,500 MW Tarali pumped storage project in Maharashtra has obtained all necessary statutory approvals and construction began only after securing requisite clearances, amid a state forest department order directing an immediate halt to work over the absence of prior wildlife clearance.
The pumped storage project has come under regulatory scrutiny over allegations that construction began without mandatory wildlife approval and questions over a sharp discrepancy in the project’s declared cost.
The Maharashtra Forest Department on November 13 ordered an immediate stoppage of all ongoing work at the project in Satara district, stating that the company started construction without prior approval from the National Board for Wildlife (NBWL).
Adani Green Energy’s Tarali Pumped Storage Project is a proposed 1,500 MW hydropower storage facility on the Tarali dam reservoir in Maharashtra’s Satara district.
The project covers 150.74 hectares of non-forest land across Nivade, Tondoshi, Kalambe and Jalu villages in Patan taluka.
Pumped storage projects use electricity to pump water from a lower reservoir to an upper reservoir when power supply is abundant. The stored water is subsequently released to generate electricity when demand rises.
The forest department's action follows allegations that the company started executing the project without mandatory prior NBWL approval, given that the area falls within the deemed Eco-Sensitive Zone of the Sahyadri Tiger Reserve.
In show-cause notices issued to the project manager and the company’s project signatory, forest officials sought an explanation on the authority under which construction had commenced without NBWL approval.
The department also demanded copies of statutory clearances, project maps and permissions for tree cutting, warning of legal action if the company failed to provide a satisfactory response within three days.
The development has also brought scrutiny on the project's estimated cost.
According to a report in The Indian Express, the company sought to revise the project's cost from ₹5,675 crore to ₹56.75 crore, a reduction to one-hundredth of the original estimate. The revised cost was accepted by the Maharashtra Forest Department.
The reduction would also proportionately lower the amount payable towards wildlife sanctuary conservation and protection, from ₹227 crore to ₹2.27 crore, the report said.
The company's revised estimate was submitted through a notarised affidavit dated September 8, 2026.
Following acceptance of the revised cost, AGEL deposited ₹56.75 lakh, equivalent to 1 per cent of the revised estimate, into the Sahyadri Tiger Reserve bank account. The balance amount is to be deposited after NBWL approval, the report said.
Maharashtra’s Principal Chief Conservator of Forests (Wildlife) M Srinivas Reddy had initially asked the company in March 2026 to deposit ₹227 crore and fulfil other conditions before the proposal could be forwarded to the NBWL.
On October 12, he informed the company that the revised figure had been accepted for the purpose of the wildlife clearance process and asked it to deposit 1% of the revised amount, or ₹56.75 lakh. The remaining 3%, amounting to ₹1.7075 crore, would be payable after NBWL approval, according to documents reported by The Indian Express.
Adani Green has said the project has obtained the necessary statutory approvals and construction began only after the requisite permissions were secured.
In a statement, an AGEL spokesperson said no component of the project falls within any notified protected area and no forest land is involved.
"No component of the Tarali Pumped Storage Project falls within any notified Protected Area and no forest land (NOC for no forest land received on 23.01.2024) is involved in the project," the spokesperson said.
It also received Environmental Clearance (EC) on February 11, 2025, followed by Consent to Establish (CTE) from the Maharashtra Pollution Control Board on April 7, 2025, it said.
"The construction activities have commenced only after obtaining all the requisite approvals from concerned authorities," the spokesperson said.
On the wildlife clearance issue, AGEL said the process had been initiated and pursued as part of the compliance requirements under the environmental clearance.
The proposal for survey and investigation activities was submitted in January 2025 and subsequently recommended by the State Board for Wildlife, it said.
The company has also submitted a clearance proposal covering the total project cost to the National Board for Wildlife, which is currently under consideration by wildlife authorities.
"The project is being developed in full compliance with applicable statutory requirements and the directions of the competent authorities," the spokesperson said.