Personal Finance News

5 min read | Updated on February 23, 2026, 18:22 IST
SUMMARY
In this case, despite the payment of almost the entire sale consideration by the homebuyers, the possession was not delivered within the stipulated or even the extended contractual period. Therefore, the homebuyers filed consumer complaints before the NCDRC, seeking delivery of possession and compensation for the delay.

SC says failure to obtain the occupancy certificate constitutes a deficiency in service. | Image source: Shutterstock
A recent Supreme Court judgement offers three important takeaways for homebuyers stuck in delayed housing projects and struggling to secure adequate compensation from the concerned real estate developers.
First, developers cannot limit or delay compensation for the delay in handing over the flats to homebuyers based on one-sided contracts.
Second, developers must obtain the occupancy certificate (OC) in a time-bound manner. They can't keep delaying forever unless there are reasons genuinely not attributable to them.
Third, subsequent buyers of flats in delayed projects are entitled to seek the same relief as the original allottee.
The above three takeaways are from the judgement in Parsvnath Developers vs Others, delivered on February 20, 2026, by a division bench of the Supreme Court comprising Justice BV Nagarathna and Justice R Mahadevan.
Let's see the case background and key observations by the apex court in the judgement in detail.
The respondents (homebuyers) had booked residential apartments with the appellant (developer) in the Parsvnath Exotica project Sector53, Gurgaon. As per the flat-buyer agreements, the possession of the flats was required to be delivered within 36 months from the commencement of construction of the respective blocks, with a grace period of six months.
Despite the payment of almost the entire sale consideration by the homebuyers, the possession was not delivered within the stipulated or even the extended contractual period. Therefore, the homebuyers filed consumer complaints before the National Consumer Disputes Redressal Commission (NCDRC), seeking delivery of possession and compensation for the delay.
Before the consumer forum, the developers attributed the delay to factors such as the "lack of adequate financial resources, shortage of labour, escalation in manpower and material costs, and statutory approvals and procedural compliances."
However, the NCDRC ruled in favour of the homebuyers, holding that the builder could not be permitted an indefinite period to obtain the Occupancy Certificate, and it was required to do so in a time-bound manner at its own cost and responsibility.
The consumer forum directed the developer to:
Complete construction of the flats
Hand over possession to the homebuyers within the specified after obtaining the occupancy certificate
Pay compensation at the rate of 8% per annum from the respective cut-off dates till actual delivery of possession
Extend rebate for the specified period at the contractual rate
Pay litigation costs of ₹25,000
Bear any increase in stamp duty occurring after the stipulated dates.
However, the developer appealed against the NCDRC order before the SC.
Before the SC, the developer argued that compensation should be restricted to the nominal rate specified in the Flat Buyer Agreement (₹10 per sq. ft. per month).
However, the apex court noted that the contract was entirely one-sided, as it allowed the developer to charge 24% interest for delayed payments from buyers while offering nominal compensation for its own delays.
"A reading of Clause 10(c) reveals that compensation for delay is stipulated at the rate of ₹10 per sq. ft. per month. Whereas, Clause 5(b) of the Agreement empowers the developer to charge interest at 24% per annum for delayed payments by the allottee and to forfeit a substantial portion of the earnest money. Thus, the terms are evidently one-sided and have been drafted unilaterally by the developer."
The top court cited Pioneer Urban Land & Infrastructure Ltd v. Govindan Raghavan, where it had held the following;
One-sided and unreasonable clauses in builder-buyer agreements constitute an unfair trade practice under Section 2(1)(r) of the Act.
Incorporation of such oppressive terms in a standard form contract, where purchasers have little or no bargaining power, cannot bind the consumer.
In the past, the apex court has held that the failure to obtain the requisite occupancy certificate constitutes a deficiency in service, entitling consumers to seek compensation.
"In view of these authoritative pronouncements, possession without an Occupancy Certificate cannot be forced upon the respondents. Obtaining such certificate is a statutory pre-condition integral to lawful delivery of possession," the apex court said.
The judgment also clarified that a subsequent purchaser is entitled to seek the exact same relief as the original allottee. The right to claim compensation for deficiency in service travels with the allotment.
"...a subsequent purchaser is entitled to seek the same relief as the original allottee and cannot be denied compensation merely on the ground that he or she stepped into the shoes of the original allottee at a later stage. The right to claim compensation for deficiency in service travels with the allotment, unless expressly barred," the apex court said citing Laureate Buildwell Private Limited v. Charanjeet Singh.
"Accordingly, we find no merit in these appeals. The orders of the NCDRC are hereby affirmed. The appellant is directed to obtain the requisite Occupancy Certificate and hand over possession to the respondents...within a period of six months from the date of this judgment. Till such time, the appellant shall continue to pay compensation as determined by the NCDRC without any default," the division bench said.
If the developer is unable to obtain the Occupancy Certificate within six months on account of bona fide causes not attributable to it, it may approach the NCDRC for appropriate consideration, limited to the issue of interest for the period after six months, according to the judgement.
Related News
By signing up you agree to Upstox’s Terms & Conditions
About The Author

Next Story
By signing up you agree to Upstox’s Terms & Conditions